OPERATION TESTS AFTER INSTALLATION
3.
Test of IP-LINK lamp on IPTRK circuit card:
a.) See if the IP-LINK lamp on the IPTRK circuit card is lighting green. This
lamp will light if the circuit card is physically connected to the IP network.
b.) When the IP-LINK lamp is OFF, make sure that the Ethernet cable is securely
connected to the IPCON connector. Make sure that neither the Ethernet cable
nor the router are faulty. If necessary, replace the Ethernet cable.
4.
Test of L1 lamp on IPTRK circuit card:
a.) See if the L1 lamp on the IPTRK circuit card is lighting green. This lamp will light if the FCCS
network link is established.
b.) When the L1 lamp is OFF, make sure the office data was correctly assigned. If necessary, replace
the circuit card.
5.
Test of IP-LRR lamp on IPTRK circuit card:
a.) See if the IP-LRR lamp on the IPTRK circuit card is lighting green. This lamp will light if the IP
network is available for connection establishment.
b.) When the IP-LRR lamp is OFF, make sure that the related office data is correctly assigned. Make
sure that each IP address assigned on the AGIP command is correct.
6.
Test of F-LINK lamp on IPTRK circuit card:
a.) See if the F-LINK lamp on the IPTRK circuit card is lighting green. This lamp will light if the
circuit card is physically connected to the FCCS network. 
b.) When the F-LINK lamp is OFF, make sure that the Ethernet cable is securely connected to the
FCON connector. Make sure that neither the Ethernet cable nor the router are faulty. If necessary,
replace the Ethernet cable.
7.
Test of F-LRR lamp on IPTRK circuit card:
a.) See if the F-LRR lamp on the IPTRK circuit card is lighting green. This lamp will light if the
FCCS network is available for connection establishment.
b.) When the F-LRR lamp is OFF, make sure that the related office data was assigned correctly.
Make sure that each IP address assigned on the AETH or AGIP command is correct.
8.
Test of Speech Conditions with Distant Nodes:
a.) Perform the connection tests to see if speech can be made with the counterparts of the connected
nodes.
b.) If any test result is abnormal, make sure the related office data was assigned correctly.
9.
Test of System Messages:
a.) When an IPTRK circuit card is installed, the following messages may be created:
23-S
FCCS FAILURE
23-T
FCCS FAILURE RECOVERED 
Note
b.) When any of the messages above are created, make sure that the Ethernet cable is securely
connected to the IPCON/FCON connector (on the IPTRK circuit card), or perform the continuity
test of the cable (voltage and resistance measurement), using a voltmeter.
Note:
Although this message is issued soon after performing system/circuit card initialization, it does not
necessarily mean a result of fault information. In this case, the message generally indicates the placement
of the IPTRK circuit card in to normal operation mode.
ATTENTION
Contents
Static Sensitive
Handling
Precautions Required