Steps to set up a 
VCStack
There are no set rules regarding the order in which stack configuration 
tasks need to be carried out. However, these steps provide a guideline to 
help ensure that the stack creation process goes smoothly.
1. Prepare the switches
Before connecting any of the switches together ensure that all switches 
have the same feature licences installed. If you have purchased feature 
licences to enable certain features to operate on the stack, then all stack 
members need to have the licences installed. If some stack members have 
feature licences installed for features that will not be used on the stack, 
and other switches do not have those licences installed, remove those 
unnecessary licences.
2. Install and power the stack master
Install and power up the master switch. It will detect that there are no other 
members in the stack, so it will elect itself master.
3. Install and power the backup member
Install the next switch, connecting the stacking cable from that switch to 
the master.
Note
Make sure the stacking cables are crossed over between the stack 
members. This means that stack port 1 on switch 1 should connect 
to stack port 2 on switch 2. If this is not done, the stack links will not 
come up and the stack will not form.
Power up the switch. It will detect that there is already an active master, 
and so will come up as a backup member. The active master will assign it 
the first available stack ID.
The active master will check that the new stack member has the same 
software version as itself. If the software versions are different, the active 
master will use the software auto-synchronization mechanism to force the 
new stack member to run the same software version.
4. Install and power the next backup member
Repeat step 3 for each of the other switches in the stack, remembering to 
connect port 2 of each new switch to port 1 of its neighbor. For last switch 
added to the stack, connect port 1 of this switch to port 2 of the first 
installed switch.
5. Confirm that the stack is operating
Check that the stack links have all come up successfully. This can be done 
by checking the LEDs on the switches. The port LEDs for all stack