 Powering up the system and initial loading
NN43021-310
Standard 02.01
December 2007
6
Clear the display and minor alarms on both Cores:
7
Test the clocks:
a.
Verify that the clock controller is assigned to the active Core:
8
Verify that the Clock Controllers are switching correctly:
9
Check applications (CallPilot, Symposium, Meridian Mail, and so on.).
10 Check dial tone.
End of Procedure
STAT XSM
Check the system monitors
****
Exit program
LD 135
Load program
CDSP
Clear displays on the cores
CMAJ
Clear major alarms
CMIN ALL
Clear minor alarms
LD 60
Load program
SSCK x
Get status of the clock controllers (x is “0” or “1” 
for Clock 0 or Clock 1)
SWCK
Switch the Clock (if necessary)
****
Exit program
SWCK
Switch Clock
(Wait 30 seconds)
SWCK
Switch Clock again