2. Behind control carrier A of EPN cabinet 3:
■
Install a lightwave transceiver on the cable connector at slot 3A01.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
300A Lightwave Transceiver
■
Connect the remaining end of the fiber cable to the transceiver just
installed.
installed.
■
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
through the cable manager to the PDS cross-connect facility.
■
Connect the fiber cable to the lightguide interconnect unit provided.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
the cable tray at the built-in cable tie positions.
■
Coil up the surplus fiber cable and place it in the cable manager.
3. Behind control carrier A of EPN cabinet 2:
■
Install a lightwave transceiver on the cable connector at slot 2A02.
■
Connect a fiber optic cable to the transceiver just installed.
■
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
through the cable manager to the PDS cross-connect facility.
■
Connect the fiber cable to the lightguide interconnect unit provided.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
the cable tray at the built-in cable tie positions.
4. Behind control carrier A of EPN cabinet 3:
■
Install a lightwave transceiver on the cable connector at slot 3A02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
300A Lightwave Transceiver
■
Connect the remaining end of the cable to the transceiver just
installed.
installed.
■
Route the cable to the cable tray and down, out of the cabinet,
through the cable manager to the PDS cross-connect facility.
through the cable manager to the PDS cross-connect facility.
■
Connect the fiber cable to the lightguide interconnect unit provided.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
the cable tray at the built-in cable tie positions.
■
Coil up the surplus fiber cable and place it in the cable manager.