Installing the Spectralink 8000 
SVP Server 
As shown in the system diagram the SVP Server is connected to the 
Ethernet switch. The specifications covered here allow for great 
flexibility in physical placement of the components within stated 
guidelines. 
Required Materials 
The following equipment must be provided by the customer.  
†  Power Outlet
 – AC adapter provided by Polycom 
†  Backboard space
 – The SVP Server is designed to be wall- 
mounted to 3/4" plywood securely screwed to the wall.  
†  Screws
 – Required to mount the SVP Server to the wall. Four #8 
3/4" panhead wood screws (or similar device) are required. 
†  Cat. 5 Cable
 – RJ-45 connector at the SVP Server. Connection to 
Ethernet switch. 
Locate the SVP Server 
The SVP Server measures approximately 4 x 12.5 x 7 inches, and 
weighs about five pounds. The unit can be wall mounted, vertically or 
horizontally, over ¾" plywood. The SVP Server can also be rack 
mounted using a rack mount kit (sold separately). 
Locate the SVP Server in a space with: 
• 
Sufficient backboard mounting space (for wall mount) and 
proximity to the LAN access device (switched Ethernet hub) and 
power source.  
• 
Easy access to the front panel, which is used for cabling.  
PN: 1725-36032-001_F.doc 