Hobart OV500E1 Leaflet

Page of 2
ASSEMBLY & START-UP 
SCOPE OF WORK GUIDE
 
 
 
 
 
 
 
 
 
 
 
 
 
SCOPE OF WORK 
Standard installation charges are included in the original Bakery order and are released 
at time of shipment. Some divisions have negotiated with Hobart to do additional 
installation work. These services are on a division-by-deviation basis and are invoiced 
locally to the division. 
 
Hobart offices will be notified prior to shipment of bakery oven and proofer. It will include 
the project manager’s name and phone number. The installing office should contact that 
person to schedule installation. 
 
After Hobart has equipment set in place, they should notify their Kroger contact that the 
utilities are ready for connection. They should also arrange to be notified when utilities 
are completed and Kroger is ready for Hobart to perform the start-up. 
 
Any questions regarding orders, or ship dates should be directed to Karen DeHart in 
Troy, OH. (937-332-2408). 
 
KROGER/GENERAL CONTRACTOR RESPONSIBILITIES: 
•  Receive, unload and store equipment within a reasonable working distance near the 
final installation location 
•  Apply for any local permits that may be required 
•  Connect required utilities to equipment upon completion of equipment assembly 
•  Supply Gas Regulator (Unit requires 11” Water Column) 
•  Provide for removal of all debris from property. Hobart will remove debris from 
installation site to dumpster location 
•  Schedule equipment installation with local Hobart Service Office 
OV500G1 SINGLE RACK OVEN – GAS 
OV500G2 DOUBLE RACK OVEN – GAS 
OV500E1 SINGLE RACK OVEN – ELECTRIC 
OV500E2 DOUBLE RACK OVEN – ELECTRIC
 
 
Procedures and Scope of work for installing an OV500 
Rack Oven. 
 
For details, refer to the Owner/Operator manual or 
Quick Reference Guide