Sun Microsystems 3900 Series User Manual

Page of 162
Chapter 3
Troubleshooting the Fibre Channel Links
33
For Internal Use Only
Note –
You can find procedures for restoring virtualization engine settings in the
Sun StorEdge 3900 and 6900 Series Reference Manual.
To Verify the A2/B2 FC Link
You can check the A2/B2 FC link using the Storage Automated Diagnostic
Environment, Diagnose—Test from Topology functionality. The Storage Automated
Diagnostic Environment’s implementation of diagnostic tests verifies the operation
of user-selected components. Using the Topology view, you can select specific tests,
subtests, and test options.
Refer to Chapter 5 of the Storage Automated Diagnostic Environment User’s Guide for
more information.
FRU Tests Available for A2/B2 FC Link Segment
The
linktest
is not available.
The switch and/or GBIC—
switchtest
test:
Can be used only in conjunction with the loopback connector.
Cannot be cabled to the virtualization engine while
switchtest
runs.
No virtualization engine tests are available at this time.
To Isolate the A2/B2 FC Link
1. Quiesce the I/O on the A2/B2 FC link path.
2. Break the connection by uncabling the link.
3. Insert the loopback connector into the switch port.
4. Run
switchtest
:
a. If the test fails, replace the GBIC and rerun
switchtest
.
b. If the test fails again, replace the switch.