The microKool portable chillers provide a Test Mode that tests
displays and keys on the control panel, as well as inputs and
outputs. The Test Mode also allows calibration of the supply
and return line thermocouples.
System tests and calibration should be performed annually.
To enable Test Mode:
Press          to shut down the chiller.
Disconnect and lock out main power to the unit,
then open the electrical enclosure. 
Set dip switches 3 and 
5 to OFF.
Set dip switch 6 to ON.
Close the electrical enclosure and restore
power to the unit.
◆ The control displays “tSt.”
◆ The Test Mode LED lights.
Press any button to display the first test menu.
Test mode provides the following menus:
● Key/Display Test
● Input Test
● Output Test
● Calibration
● Total Operating Hours
● Output Monitor Enable/Disable
After performing each test, hold the Setpoint      
for 3 seconds to index to the next test menu.
The procedure for each test is described on the following
pages.
P
ERFORMING
S
YSTEM
T
ESTS
UGH004/0999
microKool Portable Chillers
M
AINTENANCE
5-7
Stop
1
2
3
4
5
6
7
8
1
2
3
4
5
6
7
IMPORTANT: All normal
operating functions are 
disabled while Test Mode is
enabled. To return to normal
operation, you must disable
Test Mode.
To disable Test Mode,
repeat steps 2 through 5,
setting dip switch 6 to OFF
instead of ON.