Extreme 12800 Installation Guide
Extreme Networks 325 W AC Power Supply
BlackDiamond 12800 Series Switches Hardware Installation Guide
95
Do not put your hand into an open power supply bay when a power supply is not present. Empty power supply bays
require a cover plate at all times.
require a cover plate at all times.
You need the following tools and equipment to install or remove an Extreme Networks 325 W AC PSU:
●
ESD-preventive wrist strap
●
Power supply cord (110 V AC, 220 V AC, or applicable to country of use)
●
#2 Phillips screwdriver
●
Thermal protective gloves (required for removal)
NOTE
A minimum of two Extreme Networks 325 W AC PSU are required to run a BlackDiamond 12802 switch.
Installing an Extreme Networks 325 W AC PSU
CAUTION
Make sure that the Extreme Networks 325 W AC PSU circuit is not overloaded. Use proper over-current protection,
such as a circuit-breaker, to prevent over-current conditions.
such as a circuit-breaker, to prevent over-current conditions.
To install an Extreme Networks 325 W AC PSU:
1
Attach an ESD-preventive wrist strap to your wrist and connect the metal end to the ground
receptacle on the top-right corner of the switch front panel.
receptacle on the top-right corner of the switch front panel.
2
Make sure that the Extreme Networks 325 W AC PSU is right side up (see
Figure 56: Extreme Networks 325 W AC PSU
3
Carefully slide the Extreme Networks 325 W AC PSU all the way into an open power supply bay
(see
(see
) until you hear a click.
Extreme Networks recommends that you populate the two left power supply bays before the two
right power supply bays. Refer to
right power supply bays. Refer to
for the recommended installation sequence.
Torino AC PSU_04
325W AC PSU