Verifying the Securing Location
Verifying the recommended space also ensures that you have enough space available to perform the initial installation of the chassis
and its components.
Before moving the chassis into position, make sure that you have properly prepared the site so that there is sufficient room for
installation and maintenance.
The floor plan for the Cisco CRS 8-slot line card chassis must include enough space to install the chassis in the equipment rack and
allow sufficient airflow for the system. The floor plan must also provide enough room to access chassis components for maintenance
(for example, to remove fan trays, power modules, cables, and air filters).
For chassis installation, make sure that enough room exists in front of the chassis to accommodate installation personnel and the
lifting device used to hold the chassis in the rack while it is bolted to the rack.
The following figure shows the service area flooring in a lab from the top of the chassis.
Figure 2: Cisco Lab Service AreaTop View
For details on making your site ready for the chassis, see
.