Cisco Cisco CRS-X Multishelf System Installation Guide

Page of 60
This unit might have more than one power supply connection. All connections must be removed to
de-energize the unit. Statement 1028
Warning
This product requires short-circuit (overcurrent) protection, to be provided as part of the building installation.
Install only in accordance with national and local wiring regulations. Statement 1045
Warning
To prevent the system from overheating, do not operate it in an area that exceeds the maximum
recommended ambient temperature of:40°C (131°F) Statement 1047
Warning
Stability hazard. The rack stabilizing mechanism must be in place, or the rack must be bolted to the floor
before you slide the unit out for servicing. Failure to stabilize the rack can cause the rack to tip over.
Statement 1048
Warning
General Power and Grounding Requirements
This section describes the power and grounding requirements you must consider when planning the site facilities for the PDU.
A certified electrician should review the information in these sections to ensure that the installation site
meets these requirements. For larger system configurations, consult a facilities electrical expert to determine
the load that the routing system may put on the facility power plant.
Note
• Installation of the PDU must follow national and local electrical codes:
◦In the United States—United States National Fire Protection Association (NFPA) 70 and United States National Electrical
Code (NEC)
◦In Canada—Canadian Electrical Code, part I, CSA C22.1
◦In other countries—International Electrotechnical Commission (IEC) 60364, parts 1 through 7
• Two separate and independent AC power sources are needed to provide 2N redundancy for system power. Each power source
requires its own circuit breaker.
• Each power source must provide clean power to the site. If necessary, install a power conditioner.
• Site must provide short-circuit (over-current) protection for devices.
• Proper grounding is required at the site to ensure that equipment is not damaged by lightning and power surges. In addition, a
grounding-type AC power outlet is required for AC-powered systems.
• Include power requirements for any external terminals and test equipment used with your system when planning for the power
for the site.
16