SGSN in a 2.5G GPRS Network   
▀  How the 2.5G SGSN Works 
 
▄  SGSN Administration Guide, StarOS Release 18 
   
5.  Once equipment check is complete, the SGSN communicates with the HLR to update UE location information. 
6.  The SGSN then sends an Attach Complete message to UE. 
7.  SGSN begins sending M-CDR data to the CG. 
For PDP Activation 
The following provides a step-by-step illustration indicating how the 2.5G SGSN handles a PDP activation procedure. 
Figure 15.  PDP Activation Procedure 
 
1.  A PDP Activation Request message is sent from the UE to the SGSN by the BSS over the Gb interface. This 
request includes the Access Point Name (APN) the UE is attempting to connect to. This is typically a Frame 
relay connection. 
2.  The SGSN queries the DNS server to resolve the APN to the IP address of the GGSN to use to establish the PDP 
context. 
3.  The SGSN sends a Create PDP Context Request message to the GGSN. This message identifies the APN the UE 
is attempting to connect to and other information about the subscriber. 
4.  The GGSN performs its processes for establishing the PDP context. This may include subscriber authentication, 
service provisioning, etc. The GGSN eventually sends an affirmative create PDP context response to the SGSN 
containing the IP address assigned to the UE. 
5.  The SGSN sends an Activate PDP Context Accept message back to the UE. The subscriber can now begin 
sending/receiving data.