Cisco Model GS7000 4-Port Node 1 GHz with 42 54 Split Installation Guide
Applying Power to the Node
OL-29643-02
93
4 The next step depends on the power path, as follows:
IF... THEN...
power will pass from left side of housing
(Ports 1, 2, and 3) to right side of housing
(Ports 4, 5, and 6)
(Ports 1, 2, and 3) to right side of housing
(Ports 4, 5, and 6)
ensure that the AC segmentable
shunt is installed.
shunt is installed.
power is to be blocked between left side of
housing (Ports 1, 2, and 3) and right side of
housing (Ports 4, 5 and 6)
housing (Ports 1, 2, and 3) and right side of
housing (Ports 4, 5 and 6)
ensure that the AC segmentable
shunt is removed.
shunt is removed.
Ports 1, 2, and 3 are powered from one source
and Ports 4, 5 and 6 are powered from another
source
and Ports 4, 5 and 6 are powered from another
source
ensure that the AC segmentable
shunt is removed.
shunt is removed.
5 Continue to Voltage Check Procedure.
Voltage Check Procedure
Always check both AC and DC voltages during initial setup of the GS7000 Node.
Follow these steps to check AC and DC voltages.
1 Use a true-rms DVM to check for 45 to 90 V AC input voltage at the AC test point
Follow these steps to check AC and DC voltages.
1 Use a true-rms DVM to check for 45 to 90 V AC input voltage at the AC test point
on the power supply module.