Cisco Headend System Release 2.7 Release Notes

Page of 38
 
Chapter 2    Site Requirements 
 
 
 
20 
4035750 Rev A 
Process 
Length of Time 
Activity 
Pre-upgrade 
3-4 hours 
Backing up the system: 
 
Back up the system components 
 
Back up the DNCS and Application Server files 
 
Complete system checks 
These activities do not impact the system. 
Upgrade 
6-8 hours total; 
2-3 of these hours 
require system 
outage 
Note: Actual time 
may vary based 
on the number of 
devices being 
upgraded. 
Upgrade the DBDS network: 
 
Back up the DNCS database 
 
Install the DNCS and Application Server 
software 
 
Determine which optional features (licensed or 
unlicensed) need to be enabled as a result of this 
upgrade 
 
Install and download the component software 
(QAM, MQAM, GQAM, and QPSK modulator) 
 
Reboot the hardware 
 
Complete functional checks 
QPSK modulator upgrades and some QAM and 
MQAM upgrades can be completed with little or no 
subscriber impact. However, 2-3 hours of the 
upgrade require system outage. 
Post-Upgrade 
3-4 hours 
Back up the system: 
 
Back up the file system 
 
Back up the DNCS database 
These activities do not impact the system. 
 
Software Configuration 
Introduction 
This section lists the software versions in each media kit supplied with SR 5.0. 
 
Antecedents 
This release succeeds and carries forward all of the enhancements, features, and 
improvements of previous system releases and related service packs. 
 
Software Versions 
The following table lists the configuration of headend components after the upgrade 
to SR 5.0.