Cisco Cisco E-Mail Manager Unity Integration Option Release Note
ICM Process Testing In The Staging Environment
Table 4
Sample Test 4-PG Fault Tolerance
Test Number:
4
Test Title:
PG Fault Tolerance
Test Purpose:
Verify that PG’s communicate with Central Controller in Simplex Mode and that PIM’s
remain active.
remain active.
Test Setup:
All PG Services start in Duplex Mode
Procedure:
1.
Ensure that PGA is Active.
2.
Ensure that PGB is Idle.
3.
Stop Service on PGA.
4.
Observe PGB change of state from Idle to Active.
5.
Start Service on PGA.
6.
Observe PGA state as Idle.
Expected Results:
1.
B Side PG maintains connectivity to the Central Contoller and the PIM is Active.
Pass:
Fail:
2.
Upon restart of A side PG, A side MDS/OPC processes notes the state change
into idle state while the B Side PG remains Active.
into idle state while the B Side PG remains Active.
Pass:
Fail:
Pass:
Fail:
Passed: (initial)
Failed: (initial)
Reason for Failure:
Remarks:
Release 6.0(0) Staging on Windows 2000
107