2.6 
System Configuration 
The UPS device and the internal backup battery make up the system. Depending on the 
site and load requirements of the installation, available options may be utilized to create 
a tailored solution. 
Planning a UPS system should include the following considerations: 
•  The total demand of the protected system shall dictate the output power rating (VA). 
Allow a margin for future expansion or calculation inaccuracies from measuring 
power requirements. 
•  Backup time required will determine the battery size needed. If the load is less than 
the UPS nominal power rating then the actual backup time will be longer. 
Here are the following backup time for each model that is based in a 100% load. 
 
Model 
Backup time Internal 
batteries 
Recharge time to 90% 
capacity 
UPS 1000VA 
7 min 
4 hours 
UPS 1500VA 
6 min 
4 hours 
UPS 2000VA 
6 min 
4 hours 
UPS 2400VA 
11 min 
4 hours 
UPS 3000VA 
5 min 
4 hours 
UPS 6000VA 
7 min 
4 hours 
 
The following configuration options are available for enhanced UPS performance: 
•  External Battery Cabinets.  (Additional  External Battery Cabinets are 
available if more back-up time is needed.) 