Burner Control/Flame Safety 
Master/Slave Arrangement 
Revision 6 
  HercuLine™ 2000 Series Actuator - Installation, Operation and Maintenance Manual 
27 
7/07  
   
Basic Flow Control 
When the process variable signal is below set point, the controller increases current (4 to 20mA) to the 
actuator input and opens the valve.  Controller set point governs valve position to obtain desired flow 
rate. 
 
 
PV
SP
4 to 20 mA
Controller
Positioner & Actuator
Linkage
Position
mA
Valve
Orifice Plate
FIC
MP
FT
 
Figure 16 Flow Diagram 
 
Hot
Actuator
Neutral
Ground
120/240
VAC
250 Ohms
1 to 5 VDC
+
-
Current Output Controller
4 to 20 mA
 
Figure 17 Interconnection Diagram 
Proportional Flow using Multiple Actuators 
Refer to flow diagram in Figure 18 and interconnection diagrams in Figure 19.  The controller governs 
flow rate in one burner.  Only that flow is measured.  Since #2 and #3 motor positions receive the same 
signal as #1 motor positioned, valves #2 and #3 will deliver the same amount of fuel.  This is true when 
the span and zero adjustment are all set the same as in curve 2 of the graph.  Other relationships between 
units exist if the span adjustment (3) for ratio or if the zero adjustment is changed (1) for bias. 
Jumper W2  
= Current 
See Figure 
27 for jumper 
location