Product Bulletin No. EOL 1031 
End-of-Sale and End-of-Life Announcement for Cisco Catalyst 6500 
Series Supervisor Engine 2, Switch Fabric Module 2, and Selected 
Accessories and Software Releases 
Cisco Systems
®
 announces the end-of-sale and end-of life dates for the Cisco
®
 Catalyst
®
 6500 Series Supervisor Engine 2, 
Switch Fabric Module 2, selected accessories and software releases. The last day to order the affected products is March 1, 
2007. Customers with active service contracts will continue to receive support from the Cisco Technical Assistance Center 
(TAC) until February 28, 2012.
Table 1 describes the end-of-life milestones, definitions, and dates for the affected products. Table 2, Table 3, Table 4, Table 5, and Table 6 list the 
product part numbers affected by this announcement.  
Customers are encouraged to migrate to the Cisco Catalyst 6500 Series Supervisor Engine 720 or Cisco Catalyst 6500 Supervisor Engine 32. The 
Supervisor Engine 720 has a higher performance with integrated switch fabric module and supports advanced features such as IPv6, Multiprotocol 
Label Switching (MPLS), Generic Routing Encapsulation (GRE), Network Address Translation (NAT), Encapsulated Remote Switched Port 
Analyzer (ERSPAN), and so on in hardware. The Supervisor Engine 32 supports most of the same robust feature set in hardware as the Supervisor 
Engine 720 at a performance optimized for wiring closets. Please see the “Product Migration Option” section for relevant details about the 
replacement products. 
Table 1. 
End-of-Life Milestones and Dates for the Cisco Catalyst 6500 Series Supervisor Engine 2, Switch Fabric Module 2, and 
Selected Accessories.  
Milestone
 
Definition
 
Date
 
End-of-Life 
Announcement Date
 
The date the document that announces the end of sale and end of life of a product is 
distributed to the general public.
 
March 1, 2006
 
End-of-Sale Date
 
The last date to order the product through Cisco point-of-sale mechanisms. The product is no 
longer for sale after this date.
 
March 1, 2007
 
Last Shipment Date
 
The last-possible ship date that can be requested of Cisco and/or its contract manufacturers. 
Actual ship date is dependent on lead time.
 
May 31, 2007 
 
End of Software 
Maintenance 
Releases Date
 
The last date that Cisco Engineering may release any final software maintenance releases or 
bug fixes. After this date, Cisco Engineering will no longer develop, repair, maintain, or test the 
product software. 
Note : From the End of Software Maintenance Releases Date to the Last Date of Support 
("Extended Period of Support"), Cisco will provide only Critical Software Support defined as 
network services impacting bugs or security vulnerabilities that have been identified by the 
customer to Cisco TAC and subsequently qualified via Cisco's normal evaluation process. 
Critical Software Support will be provided according to the following terms and conditions:  
- Cisco TAC will first use commercially reasonable efforts to work with the Customer to 
determine the locality of impact and to find a workaround for the problem.  
- If an alternative workaround is not possible during the Extended Period of Support, then Cisco 
will make commercially reasonable efforts to provide a bug fix solution to remedy the problem.  
- If despite commercially reasonable efforts Cisco is unable to provide a software based 
solution, it may be necessary for the Customer to remove or upgrade the impacted software 
based systems to correct the problem. 
 
February 29, 2008