Method of Procedure 
Equipment Commissioning 
82 
RFN_3.1 Beta
 
5 Equipment 
Commissioning 
The procedures in this chapter describe how to conduct final checkout and 
system test procedures for each portion of the iDEN/802.11 RadioFrame System, 
including the iDEN Interface, the Power Plant, and the RFS. Following the 
successful completion of procedures described in this chapter, the RFS can be 
connected to the customer LAN as described in Chapter 6 “Connecting the RFS 
to the Customer LAN”. 
The procedures in this chapter are to be used in conjunction with troubleshooting 
and repair information provided in Chapter 7 Operations and Maintenance and 
the RFN document, Field Guide to the RadioFrame System. Together, these 
troubleshooting solutions and commissioning procedures provide the necessary 
information to isolate failures to a Field Replaceable Unit (FRU). This minimizes 
system downtime by quickly returning the site to normal operation. 
This chapter’s procedures check system functions and help isolate failures down 
to the FRU level. If a failure cannot be isolated after performing these tests, refer 
to Chapter 7 “Operations and Maintenance” for technical assistance information. 
5.1 iDEN 
Interface 
Perform the following procedures described in the Gen 3 Site Controller System 
Manual
, Motorola, 68P80801E30-O: 
Chapter 
Procedure Title 
5 Final Checkout 
Final Checkout Setup 
 
Powering the Site Controller Rack 
 Circuit 
Breakers 
6 System Testing 
Site Controller Startup Sequence 
 
T1 Connection Test 
 
EAS Alarm Checkout 
 GPS 
Status 
5.2 Power 
Plant 
Perform the following procedures described in the PEC 127NHL Manual,  
PECO II, 438127NHL-IBWS-PD: 
Chapter 
Procedure Title 
4 Initial Turn On and Acceptance Test Procedures 
Complete Operational Checkout 
 Alarm 
Tests 
 
BTC Probe Compensation Test