MC-Series System Installation & Testing 
Installation 
42 
RadioFrame Networks, Inc.
 
4.4.2 EAS 
While supporting the EAS, slide the EAS into the cabinet mounting position. 
Mount the EAS in the location shown in the cabinet illustration earlier in this section. 
Secure the EAS to the cabinet mounting rails using the four mounting screws provided with 
the unit. Tighten the screws to 4.5 Nm (40 in-lb). 
Connect the RFN-provided ground cable (P/N 820-0609-10; EAS to GND BAR) between the 
cabinet ground bar and the grounding lug on the rear of the EAS, and ensure the connection 
is tight. 
Connect the RFN-provided power cable (P/N 820-0616-50; EAS to PDU-EAS) between the 
EAS power and the EAS circuit breaker on the PDU.  
Connect EAS to each iSC-3 according to Nextel’s installation procedure. 
Connect the RFN-provided contact closure alarm wires from the CONTROL port on the EAS 
(RJ45) to the STATUS connectors on the PDU (Molex). 
 
For complete cabling information, refer to Appendix C Cabling Diagrams: 3-Sector Configuration. 
4.4.3 CSU 
 
Warning! 
Always connect the power cable to the CSU before connecting the power cable 
to the PDU. 
 
Remove the cabinet mounting rails from the CSU mounting location. 
While supporting the CSU, slide the CSU into the cabinet mounting position. 
Mount the CSU in the location shown in the cabinet illustration earlier in this section. As 
necessary, follow the equipment manufacturer's installation procedure for mounting the CSU 
in a 19” standard EIA-compliant rack. 
Connect the RFN-provided ground cable (P/N 820-0609-10; CSU to GND BAR) between the 
cabinet ground bar and the grounding lug on the rear of the CSU, and ensure the connection 
is tight.  