Radwin Ltd. AMWL1530 User Manual

Page of 98
WinLink 1000 Installation and Operation Manual 
Chapter 
 
2  Installation and Setup 
 
Installation and Setup 
2-3 
• 
WinLink 1000 Manager installation CD 
• 
Spare RJ-45 Connector 
IDU-E Package Contents: 
• 
  IDU-E 
• 
  110V/240V adaptor 
• 
  IDU wall-mounting drilling template 
• 
  Spare RJ-45 connector 
(Optional) IDU-C Package Contents: 
• 
IDU-C 
• 
For AC model, 110v/240 VAC with 3-prong connector cable 
• 
For DC model, –24VDC or -48 VDC with 3-pin terminal block 
connector (green) 
• 
IDU standard 1-U, 19” carrier rack 
• 
Spare RJ-45 connector 
External antenna (if ordered) 
ODU/IDU Cable at length ordered (optional)  
2.4  Installation and Setup 
Physical installation of the WinLink 1000 system installation includes 
the following steps: 
1.  Installing ODU at both sites of the link. 
2.  Installing ODU cable and connecting ODU to IDU at both sites. 
3.  Connecting power. 
4.  Installing the management program on the network management 
station. 
5.  Aligning the ODUs. 
6.  Running the Installation wizard from the management program. 
7.  Connecting user equipment to the local and remote IDUs.