Safety Instructions!
Before beginning installation work 
„
Disconnect the device from the power supply
„
Ensure against accidental restart
„
Verify isolation from the supply
„
Cover or close off neighbouring units that are live.
„
The assembly instructions provided for the device are to be 
complied with
„
Only suitably qualified personnel according to EN 50 110-1/-2 
(VDE 0105 part 100) are authorised to carry out work on this 
device/system.
„
When conducting installation work ensure that you are free of 
electrostatic charge before touching the device.
„
Connection and signal cables are to be installed so that any 
inductive or capacitive interference does not impair the 
automation functions.
„
The installation of automation devices and their operating
 
elements is to be carried out in such a way as to prevent 
unintentional operation.
„
In order to prevent cable or wire breakage on the signal side 
generating undefined states in the automation devices, 
appropriate safety measures are to be taken for the I/O coupling 
on the hardware and software side.
„
The functional earth (FE) must be connected to the protective 
earth (PE) or the equipotential bonding. The system installer is 
responsible for establishing this connection.
„
Ensure a reliable isolation of the extra-low voltage for the 24 volt 
supply. Only those power supply units that comply with IEC 60 
364-4-41, i.e. HD 384.4.41 S2 (VDE 0100 part 410) are to be 
deployed.
„
Fluctuations or deviations of the mains voltage from the nominal 
value should not exceed the tolerance limits specified in the 
technical data, otherwise malfunctions and dangerous states 
may occur.