Commissioning
06/07
225
4.999.112.593
Commissioning
Check List
Before you switch on the system and begin to operate it, it is essential to carry out the earthing procedures 
(the green-yellow earth wires must be stripped and connected).
Check List
Before commissioning the system, run through the check list to ensure that all 
preparations have been completed correctly: 
  
 System modules connected correctly? 
 
 Connection cables to the UAE sockets and exchange lines (a/b) connected correctly 
 
    on the LSA+ strips of the distributor according to diagram? 
 
 Patch cables connected correctly? 
 
 System earthed properly?
 
 UAE sockets connected correctly and telephones connected? 
For S
0
 bus operation: 
 Termination resistances fitted and connected at each final bus-UAE connection socket? 
 
 Bus cable lengths correct?