Avaya Integral 5 Easy BND AR2.X 4999108486 User Manual

Product codes
4999108486
Page of 254
Installation manual Integral 5 D/E easy
PB1 (emergency power supply)
06/07
137
4.999.112.593
Battery Test 
Testing of the charged battery
In network operation (i.e. plug-in mains unit inserted), the battery test is activated by a button accessible 
from outside.
Press key for approx. 2 sec. (release in area 4) ---> test starts (at present, preset test duration time is 
15 min.)
if the reference voltage (Umin) is not reached during the test duration time, the test is 
o.k., i.e. the PABX Integral 5 may be powered in the existing configuration for at least 
15 min. with this battery in the case of power failure.
After the successful test, the PB1 begins again with charging of the battery automatically, i.e. with the 
initialization phase (see "Charging phase (1)").
If the reference voltage (U min) is reached during the test duration time, the test is 
not o.k., i.e. the PABX Integral 5 can no longer be powered in the existing configura-
tion for at least 15 min. with this battery in the case of power failure.
This is signalled by needle pulses and the PB1 begins again with charging of the 
battery automatically
 
This needle pulse signalling remains visible until a reset of this display is executed
 
This reset is executed by pressing and holding the key approx. 4 sec. and releasing 
in area R.