Fluke Fluke 4325170 User Manual
Product codes
4325170
Earth/Ground Tester
Operation
11
Operation
The Tester is equipped with a 3-pole as well as a 4-pole resistance measurement that
renders measurements of resistances of earthing systems and measurements of the soil
resistivity of geological strata. The Tester also makes measurements with an external
current transformer, with which a measurement of single resistance branches in
interlinked networks (lightning protection and high voltage pylons with cabling) can be
performed without separating parts of the system.
renders measurements of resistances of earthing systems and measurements of the soil
resistivity of geological strata. The Tester also makes measurements with an external
current transformer, with which a measurement of single resistance branches in
interlinked networks (lightning protection and high voltage pylons with cabling) can be
performed without separating parts of the system.
R
A
2-Pole, 3-Pole Measurements
To make 2-pole or dead-earth measurements, connect a jumper between terminals H/C2
and S/P2 with the supplied connector cable. Use only the earth electrode and the
auxiliary earth electrode. Minimum distance between earth electrode (E/CD1) and
auxiliary earth (H/C2) should be at least 20 m.
and S/P2 with the supplied connector cable. Use only the earth electrode and the
auxiliary earth electrode. Minimum distance between earth electrode (E/CD1) and
auxiliary earth (H/C2) should be at least 20 m.
See Figures 3 and 4 and do steps 1 thru 4:
1. Select
3 POLE.
2. Connect the test leads.
Connect terminal E/C1 to the earth/ground system to be measured with the
supplied test lead and clip (1.5 m). Place two ground stakes in earth/dirt.
supplied test lead and clip (1.5 m). Place two ground stakes in earth/dirt.
Note
Minimum distance between earth electrode (E/C1), probe
(S/P2), and auxiliary earth (H/C2) should be at least 20 m.
(S/P2), and auxiliary earth (H/C2) should be at least 20 m.
Connect the stakes with the 25 m and 50 m cable reels to H/C2 and S/P2 as
shown in Figures 3 and 4.
shown in Figures 3 and 4.
3.
Push START.
indicates that a measurement is in progress. For a continuous
measurement, continue to push the START button.
4. indicates a completed measurement. The result is kept on the display until a
new measurement is started or the main switch is turned.