33
- disconnect the mains power cord; the green LED takes
approximately 20 s to go out.
- connect the mains lead again.  The charge will resume
and at the end of the second charge, capacity will be
optimum.
The charge time is approximately six hours for charging to
80% of the battery capacity. It is possible to top up the charge.
- disconnect the mains power cord; the green LED takes
approximately 20 s to go out.
- connect the mains lead again.  The charge will resume
and at the end of the second charge, capacity will be
optimum.
In the event of the unit not being used for some time,
recharge the battery before use.
Note: 
½ h charge provides self-sufficiency for one day of
measurements (approximately 135 measurements
lasting 15 s).
The battery should be replaced by Manumesure or by a
repairer approved by CHAUVIN ARNOUX.
Important: Replacement must be carried out using the model
recommended by CHAUVIN ARNOUX (see § 7.  To order)
5.1.3
Replacing the fuse
To check the fuse continuity, short circuit the H and E terminals
and make a measurement. If the FAULT indicator light flashes,
it means that the fuse has blown.
The fuse is on the front panel.
Using a screwdriver, turn the screw through a quarter turn
Take out the support containing the fuse
Replace the fuse (FF 0.1 A - 250 V – 6.3 x 32 - 30 kA)
Replace the support and screw it back.
5.2
Cleaning
The instrument must be disconnected from any source
of electricity.
Clean the housing of the equipment Carry out cleaning using
a damp cloth or soapy water. Do not use alcohol, solvents or
hydrocarbons.
5.3
Storage
If the C.A 6460 instrument is not used for a long period (more
than two months), remove the batteries and store them
separately.