Validation Testing Requirements
 
R
 
 
30 
mPGA604 Socket 
Mechanical Design Guide 
Typical examples of significant changes include, but are not limited to, the following: Plastic 
material changes including base material or color; contact changes including base material, plating 
material or thickness; and design modifications. 
6.7 
Quality Assurance Requirements 
The OEM’s will work with the socket supplier(s) they choose to ensure socket quality. 
6.8 Socket 
Test 
Plan 
6.8.1 
Submission of an mPGA604 Socket for Validation Testing 
The socket supplier’s mPGA604 socket will be sent to Intel’s independent test facility for socket 
validation testing. The sockets submitted must be per the drawing required in 
. Refer to 
 for production lot definition and number of samples required for validation 
testing. 
6.9 Mechanical 
Samples 
A mechanical sample of mPGA604 Socket, package, and heat sink (or suitable mockups that 
approximate size and mass of the planned heat sink) will be used during the mated socket validation 
testing. The maximum mass for mPGA604 Socket package heat sink is recommended as (but not 
limited to) 450g with the stipulation that the requirements of 
 be met. See data sheet and 
related documentation for further information on heat sinks, thermal solutions and mechanical 
support. 
6.10 Socket 
Validation 
Notification 
Upon completion of the testing and receipt of test data, Intel and/or the Intel designated test facility 
will prepare a summary report for the socket supplier and Intel that will provide notification as to 
whether the socket has passed or failed socket validation testing 
6.11 
Production Lot Definition 
A production lot is defined as a separate process run through the major operations including 
modeling, contact stamping, contact plating and assembly. These lots should be produced on 
separate shifts or days of the week. Lot identification marking needs to be provided to Intel as 
verification of this process. 
6.12 Socket 
Validation 
Socket validation must meet or exceed all guidelines called out in this spec which include: Visual 
Inspection, CTF Dimensional Verification, Electrical Resistance, Loop Inductance, Pin to Pin 
Capacitance, Contact Current Rating, Dielectric Withstand Voltage, Insulation, Durability, Porosity, 
Plating Thickness, Solvent Resistance (If Applicable), Solderability (Applicable for leaded sockets), 
Post Reliability Visual and use conditions. The use conditions target failure rates are <1% at 7 years 
and <3% at 10 years. Statistical sample sizes, taken randomly from multiple lots, for each test is 
required.