Enterasys Networks VSER-RPU-SYS User Manual

Page of 28
2-1
Chapter 2: 
Installing the Redundant Power Supply
Installation
Note: The VSER-RPU-SYS is compatible with V2H124-24 and V2H124-24T only.
The RPS may be placed on a desktop or mounted in a rack. 
Caution: DO NOT place the RPS on the floor as the case is not waterproof. It is 
recommended that this RPS be installed in a network equipment rack.
Selecting a Site
RPS units can be mounted in a standard 19-inch equipment rack or on a flat surface. 
Be sure to follow the guidelines below when choosing a location.
•  The site should:
• be at the center of all the devices you want to link and near a power outlet. 
• be able to maintain its temperature within 0 to 40 °C (32 to 104 °F) and its 
humidity within 5% to 95%, non-condensing
• provide adequate space (approximately two inches) on all sides for proper air 
flow 
• be accessible for installing, cabling and maintaining the devices 
• allow the status LEDs to be clearly visible
• Make sure that a separate grounded power outlet that provides 100 to 240 
VAC, 50-60 Hz, is within 2.44 m (8 feet) of each device and is powered from an 
independent circuit breaker. As with any equipment, using a filter or surge 
suppressor is recommended. 
Equipment Checklist
After unpacking the RPS, check the contents to be sure you have received all the 
components. Then, before beginning the installation, be sure you have all other 
necessary installation equipment.