Southbend SB1044 User Manual

Page of 8
-2-
Mfg. Since 6/10
Model SB1044
I N S T R U C T I O N S
Installation
During the installation process of your cutting 
fluid kit, you'll need the following items:
For Power Connection
•  A power source that meets the minimum
circuit requirements for this machine. 
•  A qualified electrician to ensure a safe and
code-compliant connection to the power 
source.
For Assembly
•  Phillips Screwdriver #2 
•  Cotton Rags and Silicone Sealant
•  Hex Wrenches 3, 5mm
•  Safety Goggles 
•  Wrench 27mm
Spash
Port
Tank
Trough
Power
Cord
      Guard
Shield
Drain
Hose
Connect Delivery 
Hose to Desired
Cutting Fluid Nozzle
SB1029
Chip 
Cover
Drain
Figure 2. Cutting fluid system installation.
6.  Apply silicone sealant to the mounting flange 
of the port shown in Figure 2.
7.  Using the fasteners from the machine in 
Step 5, install the port, splash guard, and 
the trough to the machine, as shown in 
Figure 2.
8.  Insert one end of the drain hose into the 
tank, and fasten the other end to the trough 
using the hose clamp.
9.  Route the delivery hose out of the way and 
fasten the delivery hose to your desired 
cutting fluid nozzle with the hose clamp.
10.  Fill the tank with premixed water soluble 
cutting fluid.
To install the cutting fluid kit:
1.  DISCONNECT THE SURFACE GRINDER 
FROM POWER.
2.  Fasten the four swivel caster wheels to the 
tank, and make sure the drain plug is tight.
Tip: Place one or more strong magnets at the 
bottom of the tank to collect fine metal 
particles from the cutting fluid.
3.  Route the pump power cord around the 
backside of the surface grinder, or fasten it 
up and away from the floor.
4.  Connect the SB1044 power cord to the 
surface grinder as outlined on the Model 
SB1029 Pump Connection Wiring 
Diagram on Page 7.
 
If the surface grinder uses a 440V power 
supply, the pump motor must be rewired as 
shown in the OPTIONAL 440V 3-PHASE 
CONNECTION diagram on Page 7.
5.  Remove the existing chip shield and drain 
cover from the table, as shown in Figure 2
Retain the fasteners to install the SB1044 
splash guard and port.
Note: For shipping purposes, the front and rear 
splash panels are fastened together with four 
wing nuts on the rear splash guard wall.