Volvo D13 User Manual

Page of 51
Section 01: ENGINE 
PA1561 
14 
 
 
FIGURE 9: ENGINE COMPARTMENT H3 COACHES (TYPICAL) 
01193
 
 
1.5  POWER PLANT ASSY. INSTALLATION 
To install a power plant assembly, follow the 
same procedure as in "Power Plant Assembly 
Removal" except in reverse order, then proceed 
with the following: 
1.  Torque the power plant cradle mounting 
bolts to 190 lbf-ft (255 Nm).  
2.  Refill cooling system with saved fluid (refer 
to Section 05 
COOLANT SYSTEM
).  
3.  Once engine fuel system has been drained, 
it will aid restarting if fuel filters are filled with 
fuel oil (refer to Section 03 
FUEL SYSTEM
). 
4.  Start engine for a visual check. Check fuel, 
oil, cooling, pneumatic and hydraulic system 
connections for leakage. Test operation of 
engine controls and accessories. 
1.6  ENGINE MOUNTS  
The power plant assembly is mounted to the 
cradle by means of rubber mounts and supports. 
Two engine support brackets are used at the 
front of the engine while two rubber mounts are 
mounted underneath the engine & radiator fan 
drive mechanism support and the engine & 
alternator support (Fig. 10). 
It is recommended that new rubber mounts be 
installed at each major overhaul. 
NOTE 
Refer to the table on the following page for 