Quantum Universal Remote 3.1.3 User Manual

Page of 414
Chapter 4  Common StorNext Tasks
Scheduling StorNext Events
StorNext User’s Guide
63
3
Click Configure. The second Schedule Events screen displays the 
selected event type and any existing schedules (
4
Click Add. The third Schedule Events screen appears.
Figure 38  Schedule Events 
Screen 3
5
In the Name field, enter a name for the new schedule.
6
Select either Days of the Week or Days of the Month
• If  you  selected  Days of the Week, select the days on which you 
want the event to run. To select multiple days, hold down the 
CTRL key when you select subsequent days.
• If  you  selected  Days of the Month, select the calendar dates on 
which you want the event to run. To select multiple dates, hold 
down the CTRL key when you select subsequent dates.
7
At the Run Time field, specify the time of day you want the event to 
begin.