DAMAGE ACTION PROCEDURE FLOWCHART 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Rack is 
damaged
Safety officer to assess and classify 
the damage  
Red Risk 
Orange Risk
Green Risk 
1. Identify damage for repair.
2. Order materials.
 
3. Ensure all locations 
affected by the damage are 
not reloaded after the goods 
are removed
Record the extent of 
the damage and re-
assess at the next 
inspection, but, 
within 12 months 
Immediately off-load 
all affected bays of 
racking and repair 
damage before re-
use. 
The necessary 
repairs or 
replacement of all 
damaged parts are 
correctly carried 
out. 
If repairs are 
not carried out 
within 4 weeks
Repair carried out 
If the severity 
of the damage 
has increased 
If there is no change to 
the damage level 
continue to monitor at 
normal inspection levels 
and intervals 
Continue in service 
Return to service 
Return to service