SECTION A
Stainless Condensing boiler working with HIGH 
Temperature Heating Device
A1. Pipe the system
1-1. Pipe the heating system and install all required 
components following installation instructions of 
Additional Heating Device, i.e. a wood boiler.
1-2. Connect the Additional Heating Device and 
Stainless Condensing boiler together as shown in 
Figure A1. If the Additional Heating Device can be 
pressurized.
1-3. Install Stainless Condensing boiler System Sensor 
on the supply side of the piping (supply side of 
Additional Heating Device) as shown in Figure A1. 
       If the Additional Heating Device CAN NOT be 
pressurized (i.e. and open system) connect the 
Stainless Condensing Boiler and Additional Heating 
Device as shown in Figure A2.
1-4. All near boiler piping requirements of the 
Additional Heating Device have to be satisfied. 
Refer to installation and operation manuals of the 
Additional Heating Device.
1-5. Manufacture recommends Additional Heating 
Device bypass valve. Close the
 
bypass valve when 
Additional Heating Device is used. When Additional 
Heating Device will not supply heat for extended 
period of time, open the bypass valve. This is 
important when Additional Heating Device is an 
outdoor wood boiler. Water from the system will 
not be cooled from circulating through the unused 
system.
1-6. Install expansion tank, air vent, and filling pipe at 
upstream (inlet) side of system pump.
A2. Connect Electrical Wires
2-1. Follow instructions in Additional Heating Device 
manuals when wiring 
(1) all high voltage wires 
and 
(2) Low voltage wires other than Call For Heat 
wire.
2-2. Follow instructions in Stainless Condensing boiler 
Installation, Operation and Maintenance Manual 
when connecting 
(1) all high voltage wires 
and 
(2) Low voltage wires other than Call For Heat 
wire.
2-3. Connect system pump to Additional Heating 
Device, if applicable.
2-4. All zone pumps and zone valves, if controlled 
by heating device, should be connected to and 
controlled by the Additional Heating Device, if 
applicable.
2-5. Remove or deactivate Low Limit control on 
Additional Heating Device, if available.
A3. Connect CH Call For Heat Wires
3-1. Install one of the supplied call for heat controls, 
AR822, onto wall.
3-2. Remove jumper in AR822 between Terminal-L1 
and Terminal-3. 
3-3. Connect Additional Heating Device and Stainless 
Condensing boiler. See Figure A3.
• Connect two wires, from room thermostat or 
from zone control board, to input T-Terminals 
(Terminal-R and Terminal-W) in AR822.
• Connect Terminal-5 and Terminal-6 in AR822 to 
Stainless Condensing boiler CH T-T terminals.
• Connect Terminal-3 and Terminal-4 in AR822 to 
CH T-T input of Additional Heating Device.
• Connect line voltage wires to Terminal-L2 and 
Terminal-L1 in AR822.
A4. Connect DHW Call For Heat wires, if applicable
4-1. Install supplied call for heat control, AR822, onto 
wall.
4-2. Remove jumper in AR822 between Terminal-L1 
and Terminal-3. 
4-3. Connect Additional Heating Device and Stainless 
Condensing boiler following Figure A4.
• Connect two wires, from hot water tank 
thermostat or from zone control board, to input 
T-Terminals (Terminal-R and Terminal-W) in 
AR822.
• Connect Terminal-5 and Terminal-6 in AR822 to 
Stainless Condensing boiler CH T-T terminals.
• Connect Terminal-3 and Terminal-4 in AR822 to 
CH T-T input of Primary Heating Device.
• Connect line voltage wires to Terminal-L2 and 
Terminal-L1 in AR822.
A5. Setting the Additional Heating Device
5-1. Set CH supply temperature setting of Additional 
Heating Device according to heating system 
requirement, i.e. 170°F. 
5-2. Set DHW supply temperature setting of Additional 
Heating Device according to hot water tank 
requirement, i.e. 180°F.
SECTION A -  STAINLESS CONDENSING BOILER OPERATING WITH HIGH TEMPERATURE HEATING DEVICE