9.2 Procedure 
Commissioning the cooling circuits 
Before the cooling circuits are charged, they must be rinsed with the cooling medium. 
 
NOTICE 
 
The maximum permissible pressure in the cooling circuit (see "Technical features") must 
not be exceeded. 
 
9.2 
Procedure 
9.2.1 
Checks 
Checks for commissioning in a current-free state 
Cooling circuit 
Make sure that the cooling circuit and the coolant meet the requirements outlined in the 
"Cooling" section of the 1FW6 Configuration Manual (1FW6 CM) for built-in torque motors, 
and that the cooling circuit is functioning correctly. 
 
Mechanical components 
●  The axis must be able to rotate freely throughout the entire rotating range. 
●  In the case of motors connected in parallel, motor installation and the installation 
positions of the stator and rotor must comply with the installation drawings and 
specifications in the 1FW6 CM. 
●  A "vertical axis (large imbalance)" requires a fully functional counterweight (this may or 
may not be provided). 
●  If a brake is provided, it must be controlled correctly. 
●  If there is a limit on the travel range, mechanical limit stops must be present and 
permanently attached at both ends of the rotating range. 
●  Moving cables must be correctly laid in a tow chain. 
 
Measuring system 
●  Incremental measuring system: 
Grid spacing _ _ _ _ _ _ _inc./rotation 
Number of zero marks _ _ _ _ _ _ 
OR 
 
1FW6 Built-in torque motors 
166
 
Configuration Manual, 05/2009, 6SN1197-0AD00-0BP7