PowerPath in a Cluster Environment
6. On each node in the cluster:
a. Verify that the service group is up and running, and use either 
the VCS GUI or the 
hagrp
 command to verify that the service 
group can successfully fail over to all hosts in the cluster.
b. Set a common minor number for every PowerPath Volume 
Manager volume in the cluster. Refer to Setting Major and 
Minor Numbers
 on page 2-13
 for information on setting the 
minor number.
c. Add other service groups as needed.
Integrating/ 
Upgrading 
PowerPath Into an 
Existing VCS Cluster
To integrate PowerPath into an existing VCS cluster:
1. On each node in the cluster, stop cluster services on the node 
using the 
hastop -local -evacuate
 command.
2. On each node in the cluster, install or upgrade PowerPath on the 
node, and, if you are using PowerPath Volume Manager, install 
the PowerPath Volume Manager VCS Agent. Refer to Chapter 1, 
Installing PowerPath.
3. If you are using PowerPath Volume Manager, configure VCS to 
recognize the PowerPath Volume Manager VCS Agent as a 
resource type by editing the 
/etc/VRTSvcs/conf/config/main.cf
 file on one node in the 
4. Use the 
hastart
 command to start cluster services on the node 
where you changed the 
main.cf
 file, and wait for the node to be 
fully reintegrated into the cluster.
5. Use 
hastart
 to start the remaining nodes in the cluster, waiting 
for each node to be fully integrated into the cluster before running 
hastart
 on the next node.