b.  Actuate  the  operating  lever  down  to  move  the 
load contacts against the standby contacts, i.e., 
load connected to the Standby source.
6.  Repeat  Step  5  several  times.  As  the  transfer  switch 
operating lever is moved slight force should be needed 
until the lever reaches its center position. As the lever 
moves  past  its  center  position,  an  over-center  spring 
should  snap  the  moveable  load  contacts  against  the 
stationary STANDBY or UTILITY contacts.
7.  Finally,  actuate  the  main  contacts  to  their  UTILITY  power 
source side, i.e., load contacts against the UTILITY contacts 
(upward movement of the operating lever).
RESULTS:
1.  If there is no evidence of binding, sticking, or excessive 
force required, refer back to flow chart.
2.  If evidence of sticking, binding, excessive force required 
to move main contacts, find cause of binding or sticking 
and repair or replace damaged part(s).
teSt 28 – check 23 and 15B WirinG/
connectionS
DISCUSSION:
An  open  circuit  in  the  transfer  switch  control  wir-
ing  can  prevent  a  transfer  action  from  occurring. 
Battery  voltage  +12  VDC  is  supplied  on  Wire  15B. 
This DC voltage is supplied to the transfer relay (TR) 
at  Terminal  Location  “A”.  The  opposite  side  of  the 
transfer  relay  (TR)  coil  (Terminal  B)  is  connected 
to  Wire  23.  Positive  12  VDC  is  present  on  this  also. 
Circuit  board  action  will  allow  current  to  flow  through 
the circuit and the (TR) is energized.
PROCEDURE/ RESULTS:
Refer to Figure 3.
1.  Remove transfer relay mounting screws so that contact 
movement can be visually observed.
2.  Set  the  generator  AUTO-OFF-MANUAL  switch  to  the 
AUTO  position. Turn  off  utility  power  supply  to  the 
transfer  switch,  simulating  a  utility  failure. Visually 
watch  the  transfer  relay  for  contact  movement. The 
relay should be energized and contact movement seen 
approximately 10 seconds after the generator starts.
a.  If  the  transfer  relay  energizes,  discontinue 
testing. Refer to flow chart.
b.  If the transfer relay does not energize, continue 
to Step 3.
3.  Set  the  generator  AUTO-OFF-MANUAL  switch  to  the 
OFF position.
4.  Remove the battery charger fuse (F3) from the transfer 
switch to disable the battery charge circuit.
*
   caution: after removing the fuse from the bat-
tery charger, wait 5 minutes before proceeding.
5.  Set VOM to measure DC voltage.
6.  Connect the negative (-) test lead to Wire 0 at the termi-
nal strip in the transfer switch. Connect the positive (+) 
test lead to Wire 15B at the terminal strip in the transfer 
switch.
a.  If voltage is present, proceed to Step 7.
b.  If voltage is not present proceed to Step 17.
7.  Connect the positive (+) test lead to Wire 23 at the termi-
nal strip in the transfer switch.
a.  If voltage is present, proceed to Step 8.
b.  If  voltage  is  not  present,  set VOM  to  measure 
resistance. 
c.  Remove  Wire  23  and  Wire  15B  going  to  the 
transfer  relay  from  the  transfer  switch  terminal 
strip. Connect the meter test leads across Wire 
23 and Wire 15B.
d.  Transfer  coil  resistance  of  approximately  115 
ohms should be measured.
e.  If  coil  resistance  is  not  measured,  remove 
Wire  23  and  Wire  15B  from  the  transfer  relay. 
Measure  across Terminal  A  and Terminal  B  of 
the transfer relay.
f.  If  coil  resistance  is  measured  repair  or  replace 
Wire 23 or Wire 15B between the terminal strip 
and the transfer relay.
g.  If coil resistance is not measured replace trans-
fer relay and retest.
8.  Connect the negative (-) test lead to the ground lug in 
the  generator  control  panel.  Connect  the  positive  (+) 
test lead to Wire 23 in the generator control panel at the 
terminal strip.
a.  If voltage is present, proceed to Step 9.
b.  If  voltage  is  not  present,  repair  wiring  between 
transfer switch and generator control panel.
9.  Remove the J2 connector from the circuit board.
10. Set VOM to measure resistance. 
11. Connect  one  meter  test  lead  to Wire  23  Pin  Location 
J2-5.  Connect  the  other  meter  test  lead  to Wire  15B 
Pin Location J2-8. Approximately 115 ohms should be 
measured. (see Figures 4 through 7, Section 4.1).
a.  If approximately 115 ohms is measured proceed 
to Step 12.
b.  If infinity or an open is measured, repair Wire 23 
between  PCB  Connector  J2  and  the  generator 
terminal strip.
c.  If  resistance  is  not  within  specification,  go  to 
Test 29 – Test Transfer Relay.
12. Reconnect the J2 connector to the PCB.
Page 76
Part 3
TRANSFER SWITCH
sEctioN 3.4
DiaGNostic tEsts