1.8.1 H
YDROSTATIC 
T
EST 
O
B
OILERS 
A
ND 
S
YSTEM
 
After completing the boiler and burner 
installation, the boiler connections, fittings, 
attachments and adjacent piping must be 
inspected for leaks by filling the unit with water.  
The pressure should be gradually increased to a 
pressure just below the setting of boiler safety 
relief valve(s). 
 
Remove the boiler tube access panels (see 
dimensional drawing in the boiler manual). 
 
Inspect the tube to header joints to be certain 
that all tube fittings are sealed.  This is 
necessary because, although the boiler is 
hydrostatically tested at the factory, minor leaks 
in fittings and at attachments can develop from 
shipping vibration or from installation 
procedures.  It is often necessary to retighten 
such fittings after installation and after the boiler 
has been operated for some time.  Replace tube 
access panels before proceeding to start boiler. 
1.8.2 T
EST 
O
G
AS 
P
IPING
 
 
Reference the gas system test under paragraph 
Gas Supply Connection, in this manual.