SERVICE CONNECTIONS:
Gas Operated Boilers
G
GasConnection - 3/4” (19mm) IPS (100 & 200K 
BTU)
G1
Gas  Connection  -  1”  (25mm)  IPS  (275  &  300K 
BTU)
CW1
Cold  Water - 3/8” (10mm) O.D. tubing  for  cold 
water to boiler. Cold water lines will have a max 
of  50PSI  (3.5  kg/cm
2
)  and  a  min  of  25PSI  (1.8 
kgcm
2
) water pressure. CAUTION: FILTER SYS-
TEM INSTALLATION INSTRUCTIONS MUST BE 
ADHERED TO WHEN CONNECTING A FILTER 
TO THIS LINE.
CW2
Cold Water - 3/8” (10mm) O.D. tubing for cold wa-
ter to condenser. Cold water lines will have a max 
of  50PSI  (3.5  kg/cm
2
)  and  a  min  of  25PSI  (1.8 
kg/cm2) water pressure.
D
Drain - Pipe full 2” (51mm) IPS to flush floor drain 
capable of receiving water flowing at a max rate 
of 5 gal. (19 liters) per minute. DO NOT MAKE 
SOLID CONNECTION TO FLOOR DRAIN.
EC
Electrical Connection - 120 volt A.C. 60Hz, 1/2” 
(13mm)  conduit  connection  or  equivalent.  Use 
wire suitable for a least 90
o
C. Amp for 115 steam 
generator controls is 2 amps.
ST
Steam Take-off - Connection for operation of ad-
jacent steam powered equipment.
 
NOTES: If equipment is installed where elevation exceeds 
2,000 feet (609.6 meters) above sea level, specify installa-
tion altitude so that proper gas orifices can be provided.
The only available space to supply utilities to the gas boiler 
is the 6” (152mm) space between the floor and the cabinet. 
Allow 3” (76mm) space from side wall and 6” (152mm) from 
real wall if adjoining walls are combustible.
CAUTION: Before connecting water to this unit, water sup-
ply should be analyzed to make sure hardness is no greater 
than 2.0 grains and pH level is within the range of 7.0-8.5. 
Water which fails to meet these standards should be treated 
by installation of water conditioner. EQUIPMENT FAILURE 
CAUSED  BY  INADEQUATE  WATER  QUALITY  IS  NOT 
COVERED UNDER WARRANTY.
WASTE LINE INSTALLATION: The drain port of the unit is 
marked with a colored tag and is located at the lower rear left 
side of the boiler as viewed from the front.  This exhaust line 
may be left open if the boiler has to be situated in a tiled floor 
depression or a tiled curb section that is equipped with drain 
facilities.  If this is not the case, then a  2” (51mm)  NPT. 
drain  line  must  be  connected  to  divert  the  exhaust  to  the 
floor drain.  If it is necessary to  use more than three elbows, 
increase the size of the waste line accordingly.
INSTALLATION INSTRUCTIONS
NOTE: 
PVC &  CPVC PIPE ARE NOT ACCEPTABLE 
MATERIALS FOR DRAINS.
WARNING: 
DO NOT UNDER ANY  CIRCUMSTANCE 
CONNECT THE EXHAUST DRAIN LINE 
DIRECTLY TO A SEWER LINE.