17/38 Installation 
Guide 
SG Series 225 & 300 kVA 
3.7 ELECTRICAL 
WIRING 
 
UPS installation and connection must be performed by qualified service 
personnel only. 
It is the responsibility of the installation technician to ensure that all local 
and national electric codes are adhered to. 
 
3.7.1  Utility input connection 
Ensure that the AC and DC external isolators are OFF and locked out to prevent 
their inadvertent operation. 
Do not apply power to the equipment prior to the commissioning by a qualified 
service engineer. 
Before any other input connection, connect and check the grounding wire.
 
 
The UPS has available input terminations for the Rectifier and Bypass
The unit may be powered from a common input source or separate input sources if desired. 
 
Separate input Rectifier & Bypass (recommended) 
The Bypass and Rectifier Inputs are to be powered from different Utility supplies (F1 and 
F2 inputs). 
In this case, when the Rectifier Input Fuses are opened, the Bypass and the Manual 
Bypass
 are supplied by the other source.
 
 
In this case, remove the interconnection links BR1,  BR2 and BR3 on the 
input terminals or bus bars. See Fig. 3.8.3-2
.
 
 
Common input Rectifier & Bypass 
The same power source is to be used for both Bypass Supply and Rectifier Input (input 
F3). 
Bear in mind that when the Utility Fuses are opened there is a supply failure to the Rectifier 
as well as to the Bypass and Manual Bypass.
 
 
In this case, the interconnection links BR1,  BR2 and BR3 on the input 
terminals or bus bars must remain connected. See Fig. 3.8.3-2
.
 
 
Separate input Rectifier & Bypass (recommended) 
Common input Rectifier & Bypass 
 
Fig. 3.7.1-1   Separate input Rectifier & Bypass
 
Fig. 3.7.1-2   Common input Rectifier & Bypass
 
 
 
1 =  Rectifier 
2 =  Inverter 
3 =  Automatic Bypass 
4 =  Manual Bypass 
6 = Load 
5 = Utility input 
7 = Battery