GE 30 Manual De Usuario

Descargar
Página de 88
 
GE
 
OPM_SGS_USM_10K_40K_0US_V010.doc 
54/88 Operating 
Manual 
SG Series 10, 20, 30 & 40 kVA 
4. Press inverter on ( I ) key on first unit. 
• 
Soft-start of Inverter, indicated with blinking LED
• 
At the end of Soft-start the LED Inverter remains lit. 
• 
In case of sufficient output power, the output will transfer to Inverter
• 
UPS output LED indicates Load on Inverter and  the  LCD  must display on the 
main screen the status LOAD ON INVERTER”.
 
 
 
First operated unit
 
All other units of the system
 
 
 
5. Press inverter on ( I ) key on all other units. 
(Do not start the next Inverter until the sequence of the previous ends) 
• 
As soon as the output power of the Inverters is sufficient to supply the Load, the 
output of the units with running Inverter will transfer to Inverter
• 
All LED’s InverterLoad on Inverter and Load supplied are ON.
 
 
 
First operated unit
 
All other units of the system
 
The LCD must display on the main screen on all Units the status 
LOAD ON INVERTER.
 
 
 
End of procedure 
 
 
 
The Battery must be charged for at least 10 hours, in order to ensure the 
full backup runtime in the case of a Utility Failure