Chapter 7      Configuring LAN Ports for Layer 2 Switching
Configuring LAN Interfaces for Layer 2 Switching
Note
Complete the steps in the 
 after performing the 
tasks in this section.
Completing Trunk Configuration 
To complete Layer 2 trunk configuration, perform this task:
Verifying Layer 2 Trunk Configuration
To verify Layer 2 trunk configuration, perform this task:
Configuration and Verification Examples
This example shows how to configure the Fast Ethernet port 5/8 as an 802.1Q trunk. This example 
assumes that the neighbor port is configured to support 802.1Q trunking:
Router# configure terminal 
Enter configuration commands, one per line.  End with CNTL/Z.
Router(config)# interface fastethernet 5/8 
Router(config-if)# shutdown 
Router(config-if)# switchport 
Router(config-if)# switchport mode dynamic desirable 
Router(config-if)# switchport trunk encapsulation dot1q 
Router(config-if)# no shutdown 
Router(config-if)# end 
Router# exit 
This example shows how to verify the configuration:
Router# show running-config interface fastethernet 5/8 
Building configuration...
Current configuration:
!
interface FastEthernet5/8
 no ip address
 switchport
 switchport trunk encapsulation dot1q
end
Command
Purpose
Step 1
Router(config-if)# no shutdown 
Activates the interface. (Required only if you shut down 
the interface.)
Step 2
Router(config-if)# end 
Exits configuration mode.
Command
Purpose
Step 1
Router# show running-config interface type
1
 
slot/port 
1.
type = ethernetfastethernetgigabitethernet, or tengigabitethernet 
Displays the running configuration of the interface.
Step 2
Router# show interfaces [type
 slot/port] 
switchport
 
Displays the switch port configuration of the interface.
Step 3
Router# show interfaces [type
 slot/porttrunk 
Displays the trunk configuration of the interface.