Q-Logic 64 Manual De Usuario

Descargar
Página de 244
4 – Installation
Installing a Switch
4-6
59043-03 A
D
4.
Slide the switch and rail assembly into the rack rails. Fasten the switch to the 
rack with two screws (10), one through each bracket.
4.2.2
Install SFP Transceivers
The switch has been validated with transceivers that support a variety of 
interconnection media. To install, insert the transceiver into the port and gently 
press until it snaps in place. To remove a transceiver, gently press the transceiver 
into the port to release the tension, then pull on the release tab or lever and 
remove the transceiver. Different transceiver manufacturers have different release 
mechanisms. Consult the documentation for your transceiver.
4.2.3
Connect the Switch to AC Power
Note:
The SFP transceiver will fit only one way. If the SFP does not install 
under gentle pressure, flip it over and try again.
WARNING!! This product is supplied with a 3-wire power cable and plug for 
the user’s safety. Use this power cable in conjunction with a 
properly grounded outlet to avoid electrical shock. An electrical 
outlet that is not correctly wired could place hazardous voltage 
on metal parts of the switch chassis. It is the responsibility of the 
customer to ensure that the outlet is correctly wired and 
grounded to prevent electrical shock.
You may require a different power cable in some countries 
because the plug on the cable supplied with the equipment will 
not fit your electrical outlet. In this case, you must supply your 
own power cable. The cable you use must meet the following 
requirements:
„
For 125 Volt electrical service, the cable must be rated at 13 
Amps and be approved by UL and CSA.
„
For 250 Volt electrical service: The cable must be rated at 13 
Amps, meet the requirements of H05VV-F, and be approved by 
VDE, SEMKO, and DEMKO.