G3vs with Intel 386 or Risc Processor to R8r
4-16
Upgrade Completion
4
Upgrade Completion
Install Remaining Hardware and Administer the
System
System
1. If the present system was removed to make room for the Release 8r
cabinet, skip to Step 3.
2. If the Release 8r cabinet was installed while the present system is in
. Return to
this section when finished.
3. Connect all new and reusable I/O cables to the Release 8r cabinet.
Cross-connect at the MDF as required.
4. Remove all reusable circuit packs from the present system and install into
the Release 8r cabinet. Install any new circuit packs into the Release 8r
cabinet.
cabinet.
5. Install fiber optic cables and administer the fiber links as needed. Refer to
DEFINITY Enterprise Communications Server Release 8 Installation and
Test for Multicarrier Cabinets.
Test for Multicarrier Cabinets.
6. Administer any new translations, as required.
Enable TTI
1. Type change system-parameters features and press
Enter
.
2. On the second screen, set the
Enabled?
field to y to activate the TTI
feature.
Check Link Status
1. Type display communication-interface links and press
Enter
. Compare it
with the earlier status.
2. Type status link
number and press
Enter
. Repeat this step for each link.
Enable Scheduled Maintenance
1. Type change system-parameters maintenance and press
Enter
. Use this
screen to enable scheduled daily maintenance.
Resolve Alarms
1. Examine the alarm log. Resolve any alarms using
DEFINITY Enterprise
Communications Server Release 8 Maintenance for R8r.