Grizzly G0450 Manual De Usuario

Descargar
Página de 60
G0449/G0450 37" Drum Sander
-11-
Serious  personal  injury  could  occur  if  you 
connect  the  machine  to  the  power  source 
before you have completed the set up pro-
cess.  DO  NOT  connect  the  machine  to  the 
power source until instructed to do so.
G0449
Amperage Draw
The 10 HP motor on the Model G0449 will draw 
the following amps:
Main Motor ............................................44 Amps
Feed Motor ...........................................2
1
/
2
 Amps
Circuit Requirements
Only connect your machine to a circuit that meets 
the  requirements  below.  Always  check  to  see  if 
the  wires  and  circuit  breaker  in  your  circuit  are 
capable  of  handling  the  amperage  draw  from 
your machine, as well as any other machines that 
could be operating on the same circuit. If you are 
unsure, consult a qualified electrician. 
Minimum Circuit Requirement .................60 Amp
Minimum Cord Requirements
A  cord  is  not  provided  with  your  machine.  For 
220V  single-phase  operation,  use  the  following 
type of cord (not to exceed 50 ft.):
Cord ............................................................3 wire
Gauge .................................................... 4 Gauge
SECTION 2: CIRCUIT REQUIREMENTS
Serious  personal  injury  could  occur  if  you 
connect your machine to the power source 
before you have completed the set up pro-
cess.  DO  NOT  connect  the  machine  to  the 
power source until instructed to do so.
220V Pre-Wired
The Model G0450 is prewired for 220V 3-phase 
operation,  but  can  be  rewired  for  440V  3-phase 
operation if needed.
Amperage Draw
The  Model  G0450  has  a  15  HP  motor  that  will 
draw the following amps at 220V 3-phase:
Main Motor at 220V ...............................40 Amps
Feed Motor at 220V .............................. 1.3 Amps
Circuit Requirements
Only connect your machine to a circuit that meets 
the  requirements  below.  Always  check  to  see  if 
the  wires  and  circuit  breaker  in  your  circuit  are 
capable  of  handling  the  amperage  draw  from 
your machine, as well as any other machines that 
could be operating on the same circuit. If you are 
unsure, consult a qualified electrician. 
Minimum Circuit Requirement 220V ........60 Amp
Minimum Cord Requirements
A  cord  is  not  provided  with  your  machine.  For 
220V  3-phase  operation,  use  the  following  type 
of cord (not to exceed 50 ft.):
Cord ............................................................4 wire
Gauge .................................................... 4 Gauge
G0450 at 220V
A fire may occur if your particular electrical 
configuration does not comply with local and 
state codes. The best way to ensure compli-
ance is to check with your local municipality 
or a qualified electrician.