Final Alignment
The procedures and tolerance requirements for final alignment are the same as those de-
scribed in the 
 section. Final alignment is performed just prior to grouting 
and machine hot check. All piping, including water and steam, must be completed, but the water 
and refrigerant charges need not be in place.
Hot Alignment Check 
General
When all machine components have reached operating temperature (after running near full 
load for from 4 to 8 hours), a hot alignment check must be made. Hot alignment check may be 
made with couplings assembled or disassembled.