VII Gas Piping 
 
   Gas piping to the boiler must be sized to deliver adequate gas for the boiler to fire at the nameplate input at a line pressure 
between the minimum and maximum values shown on the rating plate. For more information on gas line sizing, consult the 
utility or Part 2 of the National Fuel Gas Code
   Figure 26 shows typical gas piping connections to the BWF boiler. A sediment trap must be installed upstream of all gas 
controls. Install a manual shutoff valve outside the jacket and ground joint union as shown. 
   The boiler and its gas connection must be leak tested before placing the boiler in operation. When doing this, the boiler and 
its individual shut-off must be disconnected from the rest of the system during any pressure testing of that system at pressures 
in excess of ½ psi. When pressure testing the gas system at pressures of ½ psi or less, isolate the boiler from the gas supply 
system by closing its individual manual shut-off valve. 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
* State of Massachusetts Requires Manual 