Installation Procedure Overview   
▀  Site Prerequisites 
 
 
▄  ASR 5500 Installation Guide 
40 
   
Site Prerequisites 
This section summarizes power, grounding, environment, and clearance requirements that must be met prior to 
installing and operating the ASR 5500. For detailed information, refer to the Technical Specifications chapter. 
Power and Grounding 
Each PFU requires eight power feeds of 80A @ -48VDC (nominal). The feeds should be routed to the installation rack 
from the site power supply using adequately sized conductors and circuit breakers in accordance with local electrical 
codes. For additional information on power requirements, see the Technical Specifications chapter. 
The chassis must be grounded to a site ground point using the recommended conductors and lugs. The ground point 
should be in close proximity to the ASR 5500 chassis to assure adequate conductivity. 
Environment 
The site’s heating ventilation and air conditioning (HVAC) systems must be sized to maintain the operating 
temperatures and relative humidity specified in the Technical Specifications chapter. HVAC capacity requirements will 
vary based on the system configuration and associated power draw, as well as the operational characteristics of other 
equipment installed at the site. 
Clearance 
Adequate clearance must be maintained at the front and rear of the ASR 5500 chassis to assure proper air flow and 
allow maintenance access for the installation, removal and replacement of components. The recommended clearance is 
36 inches (92 centimeters) at the front and rear of the chassis.