Cisco Cisco 1 GHz GainMaker Amplifier Guía De Instalación

Descargar
Página de 132
 
Chapter 3        Balancing and Setup 
 
 
 
42 
 
Preparing for Forward Path Balancing 
Before you begin balancing, it is important to review and understand the following 
information. This information will show you which balancing process is appropriate 
for your line extender. 
Before balancing, make sure that you have configured the line extender according to 
the specifications in your design print and that the line extender has warmed up for 
approximately one hour. 
The table below shows the items needed for balancing. 
You need a ... 
To ... 
copy of the design print 
determine expected input and output signal 
levels. 
torque wrench with 1/2-inch socket 
open and close the line extender housing. 
spectrum analyzer or signal analysis 
meter capable of working with 
frequencies up to the highest design 
frequency 
determine absolute and relative signal levels. 
test point adapter or F-81 
female-to-female adapter 
access the test points. 
length of 75 ohm coaxial cable with 
F-connectors on each end 
connect the test point adapter to the test 
equipment. 
voltmeter 
test the power supply AC and DC voltages. 
reverse sweep receiver 
test signals using a reverse sweep transmitter. 
1/8-inch flat blade screwdriver 
adjust switch S1, AGC Manual Backoff, and 
AGC Gain Control 
 
Understanding BODE Switch Function 
The BODE Switch is used to set the interstage control of the Line Extender. This 
switch can be set for either Thermal control or Manual control of the Line Extender. 
The BODE is always present in the Line Extender and can be engaged for either 
Thermal or AGC operation of the product. The BODE circuit is by-passed when this 
switch is in the Manual Mode. 
Understanding Switch S1 Functions 
Switch S1 is a multifunction, three-position switch. Switch S1 functions are