WIRING DIAGRAMS
60°
Field-of-View
INSTALLATION (Continued)
3.  Prepare the photocell lead wires by removing 3/4" (1.9 cm) of 
insulation from each lead to expose bare copper wire. Make 
sure the ends of wires are straight.
4.  Determine the length of low voltage wires needed to connect 
power to photocell. Use wires suitable for low-voltage wiring 
according to local electrical codes.
5.  Route low-voltage wires from GLS-LCL location(s) to interface 
device location(s). (Refer to the wiring diagrams in the next 
column.)
6.  Prepare low-voltage wires by removing  3/4 inch (1.9 cm) of 
insulation from each lead to expose bare copper wire. Make 
sure the ends of the wires are straight.
7.  Connect low voltage wires as shown in Figure 2 (black to 
ground, red to power, and orange to the interface device). Twist 
strands of each separate wire connection tightly, and push firmly 
into appropriate wire connector. Screw connector on clockwise 
ensuring no bare conductor shows below the wire connectors. 
Secure each connector wiith electrical tape.
8.  Mount GLS-LCL to the ceiling. INSTALLATION IS COMPLETE.
TROUBLESHOOTING
PROBLEM
 
POSSIBLE 
CAUSE
 
CORRECTIVE 
ACTION
 
Incorrect wiring 
between sensor 
and GLS-SIM (or 
other compatible 
interface). 
 
 
 
 
Improper sensor 
location. 
 
Verify that sensor is 
located such that it can 
detect the desired 
workspace light levels. 
 
Lights don’t respond 
to change in ambient 
light level.
 
Improper control 
system programming. 
Check logic in control 
processor, or contact 
Crestron for assistance. 
24 1  2  G
Black
Red
Orange
Black
Red
Connecting Sensors to the GLS-SIM
Connecting Sensors to the DIN-IO8 or Equivalent*
All wires from sensor to GLS-SIM 
must be 24 AWG, minimum.
–SENSOR–
––– NET–––
24  Y  Z  G
Use CRESNET-P or 
CRESNET-NP wire only 
GLS-SIM
To Control
System
G   1   2   3   4
–––  NET
G   1   2   3   4
24  Y   Z   G
24  Y   Z   G
–––
To Control
System
–––
–––
I/O
DIN-IO8
NOTE: The same Crestron power supply MUST be 
used to power both the sensors and the interface 
device (e.g., DIN-IO8). Otherwise, there is a risk of 
damage to the interface device. 
*The following Crestron devices may be 
used to integrate the sensors into a Cresnet 
system by following the schematic shown 
here:
DIN-IO8  DIN-AP2  PAC2 
PRO2
AV2 
CP2E 
MP2E 
CNXIO16
Use CRESNET-P or 
CRESNET-NP wire only 
TYPICAL APPLICATION DIAGRAMS
GLS-LCL
GLS-LCL
GLS-SIM
Cresnet
®
DIN-IO8
Cresnet
®
Crestron
2-Series Control
Processor or 
CLS-C6
Crestron
2-Series Control
Processor
Orange
Refer to the wiring 
diagrams in the right 
column.
White**
Red**
Blue**
** 250 feet max.