installing the xmax bsn-250
To install the six units that comprise the xMAX BSN-250 Base Station:
Mount the six components of the base station as shown in Figure 1, into a standard 19-inch (480 mm)
rack that is at least 18 inches deep and 15U high.
rack that is at least 18 inches deep and 15U high.
ATTENTION
:
Be sure to follow proper safety precautions when lifting heavy equipment.
2. Two 10/100 Mbps RJ-45 Ethernet connectors are installed on the rear of the control unit. The Ethernet
ports are used to connect the base station to the backhaul network and the xMSC. Connect the Ethernet
cable to the control unit, as shown in Figure 2.
cable to the control unit, as shown in Figure 2.
1.
Figure 1: Base Station Components – Front/Side View
[Needed from xG: New image to reflect current design/labeling of the
units.]
units.]